I installed about 75% of the insulation today after receiving my framing/electric/mechanical inspection approval. It’s always nice to do something that provides a nice visual (and audible in this case) result.
Don’t mind the giant mess. I figured I’ll clean it all up after I finish the rest of the walls. It’s beginning to look like a room 😀.
The drywall is scheduled to be delivered on Monday. That gives me a week to finish the insulation and make all my finishing touches.
I really wish my monoprice order would ship already! It’s been a week which is abnormal for them. I don’t “need” anything from that order to move forward, but it would be nice to fish the HDMI cables through the conduit before I close up the wall, just in case.