Today was a productive day but another one without a ton of visual feedback. Here’s what I accomplished:
– Ran the final electric circuit (main stairwell lights/switches) and racked up some of the loose romex.

– Started cleaning up the low voltage wore and getting it into some split loom for organization and limited protection. Need to figure out if/how I’ll secure them still.
Next up will likely be checking and securing more romex, moving my subwoofer supports (I’m an idiot and put them about 8” too low), figuring out my projector conduit situation, drilling holes in the top plates for the low voltage wires to get into their homes and calling the HVAC guy. Once all of that is complete (or throughout) I’ll nail up al the nail plates and call the inspector.
Have I said how much I can’t wait to be insulating….I know, a death wish….but hey anything different at this point.